Contractors urged to ditch ‘divide and conquer’ procurement
Added 27 Nov 20263 min read

Contractors have been urged to abandon ‘divide and conquer’ procurement practices amid concerns that late supply chain involvement could add a year to design development on higher-risk building (HRB) projects.
Speaking during a panel session at the London Build exhibition on 26 November, Rob Cullen, project director at architecture firm Scott Brownrigg, called for an overhaul. He described a culture in which trades were pitted against one another and subcontractors could seek extra payments because of poorly co-ordinated designs.
“I think that the divide-and-conquer approach really can’t continue,” Cullen said.
He advocated bringing contractors on board during stage three of the Royal Institute of British Architects (RIBA) Plan of Work, under preconstruction services agreements.
Stage three covers spatial co-ordination, when architectural and engineering designs are brought together, with planning applications generally submitted at its end.
Cullen said earlier contractor involvement would enable costs to be discussed, with specialist subcontractors able to contribute to designs ahead of planning submissions.
He warned that pursuing a design-and-build procurement route without early supply chain involvement could significantly extend programmes.
“It might cost you a year in your design development,” he said.
Dan Norman, senior specification manager at facade manufacturer Obex, said the industry needed to abandon the practice of discarding product specifications late in the development process.
He advocated “nailing down” product performance, fire classification and prices with manufacturers earlier.
David Brook, technical director at architecture practice Hawkins\Brown, warned that resolving design issues during construction risked triggering statutory change-control procedures, adding costs and disrupting programmes.
He said spatial co-ordination should be completed by the end of RIBA stage three, allowing individual design disciplines to focus on technical design during stage four.
The panel also questioned established working practices during RIBA stage five, which covers manufacturing and construction.
Session moderator Paul McSoley, director of consultancy PMCSTECH Consult, pointed out that design changes during construction could effectively send project teams back to stage four to reassess technical designs.
Brook warned contractors: “If you change things on site, you’re becoming a designer.”
Cullen outlined a procurement model under which technical design could continue alongside construction, with work starting on fully designed elements once the necessary regulatory approvals were secured.
The latest Building Safety Regulator (BSR) data showed the median closure time for major change requests relating to new HRBs and conversions was seven weeks, compared with 26 weeks for internal works on existing HRBs.
Construction work relating to a proposed major change cannot proceed until the regulator has approved it.
The BSR also disclosed that inspections of new-build projects had identified some construction work that deviated from designs agreed at gateway two.
Norman highlighted the potential for a pinch point at gateway three, recalling a meeting with the BSR last year.
He said the regulator had expressed concern that contractors might press ahead with construction after securing gateway two approval without adequately preparing for gateway three.
Norman urged contractors to gather compliance evidence throughout construction and select manufacturers capable of supporting them through to final approval.
No new-build project that had passed through gateway two had reached gateway three as of 1 November, according to the regulator.
Where this story came from
This article was first published by Construction News and is reproduced here in full, with credit. All words and images remain the publisher’s work.
Read the original at Construction NewsMore on Builders & trades
- Visa grants for construction trades plunge 70%
Construction News · Added 26 Nov 2026
- Sennebogen starts work on training centre
The Construction Index · Added 24 Nov 2026
- SMEs struggle with s106 affordable home projects